We delivered this 2,100 sq m facility within eight months of receiving first instructions from Greggs. During this time the facility was designed, all necessary planning and other statutory consents were obtained and construction work completed.
The highly efficient design includes bespoke storage and order picking facilities for frozen, chilled and ambient foodstuffs together with associated staff amenities and administrative accommodation.